Wastewater & sewerage · UK

Stockport wastewater treatment works extension

Resident Engineer · 1992–1994

160 Ml/d
FTFT
41 m dia.
final tanks ×4

Scope

Construction management of process enhancements to meet river quality directives: nitrifying activated sludge plant, circular settlement tanks, inter-stage pumping, replacement sludge storage and treatment.

Close supervision of the 75 × 75 × 6 m piled FBDA aeration basin and four 41 m final tanks built by continuous thin-wall technique, holding tolerances for the rotating half-bridge scrapers.

Full commercial control: monthly valuations, variation orders, claims assessment and final account.

Outcome

Works extension performing to directive standards; final account agreed.